Model overview

The data model has two parts: what describes the operation, which changes little (plants, resources, processes), and what is planned, which changes every day (orders, proposals, plans).

Project
├─ Plant ──< Resource >── Resource type
├─ Process (template) ──< Process task
│ ├─ resource requirements (with alternatives)
│ └─ precedences (with minimum and maximum waits)
├─ Product (process + properties)
├─ Order ──< Order line (quantity, due date) ──> Product
└─ Proposal (start date, status, base plan)
└─< Planned task (resource, start, end, fixed)
Entity What it describes Page
Project A planning problem with its configuration: time unit, default objectives and constraints This one
Plant, resource type, resource Who does the work, where and with what capacity Resources
Process and process task What steps a job has, in what order and with which resources Tasks and processes
Product, order, line What has to be done and by when Orders and dates
Proposal, current plan Computed plans and the accepted plan Proposals and current plan
Planned task Each task with its resource, its start and its end Result of a plan
Field What it is
Input unit The unit in which durations are given (minute, hour, day or week)
Planning unit The unit the plan works in
Default objectives The objectives applied if a proposal does not specify otherwise
Default constraints The active constraints
Maximum computation time How long the computation of a proposal can take; the best solution found is returned

Resources, tasks and products can carry their own properties: length, weight, speed, number of parts. Durations, quantities and the choice of resources can be formulas over those properties.

cutting duration = part length / machine speed
valid resources = machines whose load capacity ≥ part weight

Formulas are validated before computing: a reference to a property that does not exist or a cycle between formulas is flagged as an error.