A product is a process with its properties already filled in: “12 m frame” is the “Frame” process with its length, its number of modules and its material. It is reused in every order that includes it.

Entity Fields
Order Customer, reference, priority or weight
Order line Product, quantity, due date

Each unit in a line becomes a job to plan, with its tasks. Each unit keeps its identity across replans, so a new plan can be compared with the previous one unit by unit.

The due date is a soft rule: the plan tries to meet it and, if it cannot, penalises the deviation.

Penalty What it measures
Lateness Each time unit the order finishes after its date
Earliness Each time unit it finishes before (producing early also has a cost: stock, space)
Order duration Time between the first and the last task (the more compact, the less work in progress)

Each penalty has a weight, and each order or customer can have its own: one customer can penalise lateness more than another. See the On-time delivery objective.

An order can be withdrawn from a plan: its capacity is freed and the rest is recomputed without touching what is already running.