Getting started

This example is the same one shown on the website: two orders, X and Y, made on two lines and then assembled.

Resource Capacity
Line 1 1 task at a time
Line 2 1 task at a time
Assembly 1 task at a time
Task Order Resource Duration Goes after
X1 X Line 1 2 h —
X2 X Line 2 1 h —
X3 X Assembly 2 h X1 and X2
Y1 Y Line 1 1 h —
Y2 Y Line 2 2 h —
Y3 Y Assembly 1 h Y1 and Y2
Rule Type How it is expressed
Precedence Hard “Goes after” on each task
Capacity Hard The capacity of each resource
Material: the sheet metal arrives at 10:00 Hard Earliest start of the line tasks
Stoppage from 13:00 to 14:00 Hard A fixed block on each resource

Finish as early as possible: the Makespan objective.

Resource Plan
Line 1 X1 10:00–12:00 · Y1 12:00–13:00
Line 2 X2 10:00–11:00 · Y2 11:00–13:00
Assembly X3 14:00–16:00 · Y3 16:00–17:00

Without the material rule the plan would start at 8:00, and without the stoppage rule the assembly of X would fall in the middle of it. Each rule discards plans that cannot be executed: that is what figure 2 on the website shows.